Current Dev Position: YP 2.7 M4 (New feature Freeze has begun.)
Next Deadline: YP 2.7 M3 Release Target was Mar. 8, 2019
SWAT Team Rotation:
Key Status/Updates:
- M3 has been built and is currently in QA
- There are a small number of upgrades which merged after M3 as it was felt better to be up to date in these cases along with various other fixes. The project is now very much in feature freeze and bug fixing working toward the final release though.
- The OpenEmbedded election for its TSC members is now in the nomination phase.
- For the stable releases, the autobuilder-helper changes have now merged and the resulttool patches are also backported on the relevant -next branches. This means we’re ready to build both 2.5.3 and 2.6.2.
Planned Releases for YP 2.7:
- YP 2.7 M3 Cutoff was Feb. 25, 2019
- YP 2.7 M3 Release Target was Mar. 8, 2019
- YP 2.7 M4 Cutoff is Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.5.3 (Sumo) will be targeted for build as soon as it is ready..
- YP 2.6.2 (Thud) will be targeted after YP 2.5.3 is done.
Tracking Metrics:
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Project Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com