Current Dev Position: YP 4.2 M2
Next Deadline: 23th January 2023 YP 4.2 M2 Build
Next Team Meetings:
Key Status/Updates:
- YP 4.2 M1 and YP 4.0.6 passed QA and are due for release.
- Builds on the autobuilder are problematic at present due to connection losses with the controller machine. We understand the cause and will be migrating the controller to a new server/location to address this.
- That, combined with OOM issues from recent bitbake cache changes meant patches are merging more slowly this week.
- There are a number of bitbake patches pending which are a bit more invasive than usual. These are aiming to address:
- memory issues seen with the recent cache changes and bitbake -S
- UI hangs where the bitbake server has crashed/hung or otherwise failed
- issues where bitbake may have removed another server instances bitbake.sock network socket file
- console interaction issues where bitbake may not respond to Ctrl+C
- event handler race issues around datastore accesses
- The OE TSC decided in favour of adding export flag expansion despite the performance impact so that patch will be queued.
- CVE levels in master are concerning again
- With some debugging, the bitbake.sock disappearance was potentially identified and also issues with OOM process killing locking up bitbake’s server and UI were studied.
- We have a growing number of bugs in bugzilla, any help with them is appreciated.
- There will be no status report next week, the next will be 3rd January 2023.
Ways to contribute:
- As people are likely aware, the project has a number of components which are either unmaintained, or have people with little to no time trying to keep them alive. These components include: patchtest, layerindex, devtool, toaster, wic, oeqa, autobuilder, CROPs containers, pseudo and more. Many have open bugs. Help is welcome in trying to better look after these components!
- There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
- There are bugs that are currently unassigned for YP 4.2. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_4.2_Unassigned_Enhancements.2FBugs
- We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
- Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT.
- Help us resolve CVE issues: CVE metrics
YP 4.2 Milestone Dates:
- YP 4.2 M1 is ready for released
- YP 4.2 M2 build date 2023/01/23
- YP 4.2 M2 Release date 2023/02/03
- YP 4.2 M3 build date 2023/02/20
- YP 4.2 M3 Release date 2023/03/03
- YP 4.2 M4 build date 2023/04/03
- YP 4.2 M4 Release date 2023/04/28
Upcoming dot releases:
- YP 4.0.6 is out of QA
- YP 4.1.2 build date 2023/01/09
- YP 4.1.2 Release date 2023/01/20
- YP 3.1.22 build date 2023/01/16
- YP 3.1.22 Release date 2023/01/27
- YP 4.0.7 build date 2023/01/30
- YP 4.0.7 Release date 2023/02/10
- YP 3.1.23 build date 2023/02/13
- YP 3.1.23 Release date 2023/02/24
- YP 4.0.8 build date 2023/02/27
- YP 4.0.8 Release date 2023/03/10
- YP 4.1.3 build date 2023/03/06
- YP 4.1.3 Release date 2023/03/17
- YP 3.1.24 build date 2023/03/20
- YP 3.1.24 Release date 2023/03/31
- YP 4.0.9 build date 2023/04/10
- YP 4.0.9 Release date 2023/04/21
- YP 4.1.4 build date 2023/05/01
- YP 4.1.4 Release date 2023/05/13
- YP 3.1.25 build date 2023/05/08
- YP 3.1.25 Release date 2023/05/19
- YP 4.0.10 build date 2023/05/15
- YP 4.0.10 Release date 2023/05/26
Tracking Metrics:
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com