* [ANN] netdev foundation TSC meeting notes - Jan 13th
@ 2026-01-13 16:46 Jakub Kicinski
2026-03-04 6:28 ` Jason Xing
0 siblings, 1 reply; 3+ messages in thread
From: Jakub Kicinski @ 2026-01-13 16:46 UTC (permalink / raw)
To: netdev, netdev-driver-reviewers
Present: Andrew, Jakub, Johannes, Kuniyuki, Simon, Willem, Paolo
PHY Testing SoW Update
- Approved by board; processing contract in conjunction with LF
Lab update
- 3 machines in production (control, build, virt/ksft)
- Have capacity to host Wireless NIPA
- HW testing - 1 of 2 stage 2 machines received, other is on back order
- ETA 2 weeks but keeps getting pushed out weekly
- 2 NICs per machine
Finance Estimates
- Estimating $200k+ EoY’26 balance
- Looking for ways to effectively use these funds
- Netconf funding was one avenue
- Patchwork extensions are still in the works
NIPA maintenance help
- Either a separate SoW for significant chunks of work or time commitment
- Prefer time commitment due to lower management overhead
- 1 day/week with possibility to extend periodically to more as task pile up
- need upper bound for budgeting
AI Review Discussion
- Delay has been implemented to discourage reposting too quickly
- Tool is being used to limited but good effect by some maintainers
and developers
^ permalink raw reply [flat|nested] 3+ messages in thread
* Re: [ANN] netdev foundation TSC meeting notes - Jan 13th
2026-01-13 16:46 [ANN] netdev foundation TSC meeting notes - Jan 13th Jakub Kicinski
@ 2026-03-04 6:28 ` Jason Xing
2026-03-04 18:06 ` Jakub Kicinski
0 siblings, 1 reply; 3+ messages in thread
From: Jason Xing @ 2026-03-04 6:28 UTC (permalink / raw)
To: Jakub Kicinski; +Cc: netdev, netdev-driver-reviewers
On Wed, Jan 14, 2026 at 12:46 AM Jakub Kicinski <kuba@kernel.org> wrote:
>
> Present: Andrew, Jakub, Johannes, Kuniyuki, Simon, Willem, Paolo
>
> PHY Testing SoW Update
> - Approved by board; processing contract in conjunction with LF
>
> Lab update
> - 3 machines in production (control, build, virt/ksft)
> - Have capacity to host Wireless NIPA
> - HW testing - 1 of 2 stage 2 machines received, other is on back order
> - ETA 2 weeks but keeps getting pushed out weekly
> - 2 NICs per machine
>
> Finance Estimates
> - Estimating $200k+ EoY’26 balance
> - Looking for ways to effectively use these funds
> - Netconf funding was one avenue
Hi Jakub,
I wonder if it's the reason why the link below seems invalid?
https://netdev.bots.linux.dev/netconf/2024/index.html
Thanks,
Jason
^ permalink raw reply [flat|nested] 3+ messages in thread
end of thread, other threads:[~2026-03-04 18:06 UTC | newest]
Thread overview: 3+ messages (download: mbox.gz follow: Atom feed
-- links below jump to the message on this page --
2026-01-13 16:46 [ANN] netdev foundation TSC meeting notes - Jan 13th Jakub Kicinski
2026-03-04 6:28 ` Jason Xing
2026-03-04 18:06 ` Jakub Kicinski
This is a public inbox, see mirroring instructions
for how to clone and mirror all data and code used for this inbox