Current Dev Position: YP 4.1 M3 (Feature Freeze)
Next Deadline: 22nd August 2022 YP 4.1 M3 Build
Next Team Meetings:
Key Status/Updates:
- We are now at feature freeze for 4.1 but M3 has not been built yet.
- Many of the blocking issues for M3 have been resolved including:
- perl build hangs
- cve-check database issues
- hash-equiv file not found issues on local domain sockets
- layer setup changes merged
- rust upgrade merged
- libgcrypt ptest issues on ARM is potentially fixed
- llvm build path corruption in mesa was resolved
- rust ppc patch was revised
- llvm-config handling in core was reworked
- nativesdk-gcc issue breaking rust SDK tests was identified and fixed
- a checksum mismatch race issue in bitbake’s fetcher code was fixed
- Thanks to everyone who helped work on and resolve these, it will significantly improve the release and autobuilder stability during testing.
- There is still an issue with rust SDK failures on ubuntu1804 to resolve before M3 can build
- The rust selftest changes are looking unlikely to merge as they don’t pass during testing yet and one of the precursor patches causes buildpath issues. Some precursor patches did merge.
- Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
Ways to contribute:
YP 4.1 Milestone Dates:
- YP 4.1 M3 build date 2022/08/22
- YP 4.1 M3 Release date 2022/09/02
- YP 4.1 M4 build date 2022/10/03
- YP 4.1 M4 Release date 2022/10/28
Upcoming dot releases:
- YP 4.0.4 build date 2022/09/19
- YP 4.0.4 Release date 2022/09/30
- YP 3.1.20 build date 2022/10/10
- YP 3.1.20 Release date 2022/10/21
- YP 4.0.5 build date 2022/10/31
- YP 4.0.5 Release date 2022/11/11
Tracking Metrics:
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com