Current Dev Position: YP 2.8 M3
Next Deadline: YP 2.8 Milestone M3 Cutoff (Feature Freeze) Aug 25, 2019
SWAT Team Rotation:
Next Team Meetings:
Key Status/Updates:
- YP 2.6.3 has been released.
- This release which was 2.8 will now become 3.0.
- The sstate hash equivalency continues to have challenges:
- performance of the hash server is not able to scale to the autibuilder’s load
- there are some bugs in the code the autobuilder continues to expose
- we have cases where its not 100% clear what the correct behaviour should be
- test cases are proving to be problematic to write in a maintainable way
- On a more positive note, some of the key performance issues were identified and fixed so performance doesn’t regress for usage without hash equivalence. Several corruption issues and other key fixes to runqueue also merged.
- Jason Wessel finally tracked down our mystery glibc-locale bug, which was not a pseudo issue. Thanks and kudos to Jason!
- General patch merging is currently delayed along with patch feedback due to the hash equivalence issues and lack of bandwidth to progress everything at once.
- We still need to make a decision on systemd or sysvinit defaults as the init system.
- We are a week away from the 3.0 feature freeze.
Planned Releases for YP 3.0 {2.8}:
- M3 Cutoff (Feature Freeze) 25th Aug
- M3 Release 6th Sept
- M4 Cutoff 30th Sept - this will be YP 3.0.
- YP 3.0 {2.8 (M4)} Final Release 25th Oct
Planned upcoming dot releases:
- YP 2.7.2 (Warrior) is planned for after YP 3.0 release.
- YP 2.6.4 (Thud) is planned for after YP 2.7.2 release.
Tracking Metrics:
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Project Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com