From mboxrd@z Thu Jan 1 00:00:00 1970 Return-Path: Received: from mail-pf1-f172.google.com (mail-pf1-f172.google.com [209.85.210.172]) by mail.openembedded.org (Postfix) with ESMTP id 760E7600BB for ; Tue, 19 Mar 2019 14:53:03 +0000 (UTC) Received: by mail-pf1-f172.google.com with SMTP id j5so13888926pfa.2 for ; Tue, 19 Mar 2019 07:53:05 -0700 (PDT) DKIM-Signature: v=1; a=rsa-sha256; c=relaxed/relaxed; d=gmail.com; s=20161025; h=from:to:subject:date:message-id:mime-version:thread-index :content-language; bh=3S459eX08rF4hLsYYDXIe7QL7PjhZWkdFw/Jqy2+xPY=; b=PuqagrCsqNrDwPMZ6yKLjhQjoxXMFbs6sHloH2Fo98MFbA24HvpgosD9Rxx1QszJQ1 doaCFXHsbxaXrvdeDlMZwtGSCpbIyXKEDFN24t8hnEymIeiyBeRMByuXPR36dj0fgNPi DMb6sil5+nnJf10QlI1n1JsSxtBoB75beJwfwc9ydYjYfq9l3gQ3VVv/gWMk/CeBwv8W /L0wcxC1XXiHYoqR2Qvnd5qVdbLZIR3A6nASolDF8oX/GXOZsxqJeYNTqQyta92uVBs3 lPqpIbkcmb55QGCnlkBfhrowRzhMBEapE0XS35XJjNv7nxdJg3rGOlTyQuhf3f+NF7jd uwnA== X-Google-DKIM-Signature: v=1; a=rsa-sha256; c=relaxed/relaxed; d=1e100.net; s=20161025; h=x-gm-message-state:from:to:subject:date:message-id:mime-version :thread-index:content-language; bh=3S459eX08rF4hLsYYDXIe7QL7PjhZWkdFw/Jqy2+xPY=; b=VJC9q3/dBGXHChTGJghAeCFpTuKfWzC3QYOA9IMNsoz8ZxXbwM+4F8h6B9W+gEfVJK iiq+BufkTfpS7IXD4Wermtq1iv1wNh6Hurq5qJ22KAmq0dR1MksZqf22VJB+DrhGb4Gd O9nc1sCnkgpaY6Hd2p3842s6IabmLLf+Mg4ifLcbHw1CnCzlTYiLNeiDtHqbTgEMuJtJ /hk9816ouWEN62S/kh+iAz87k5nXbntBtvmX6P8rqzbFlSTsT9S3FW339xs705sJbuCH v57PIgRrMyuydMcb2Eh5NRrs+LZ+ve+nJgLD9I/Ox11juUKD7FhmiJ7bD7TXDGoAV0mm pxSg== X-Gm-Message-State: APjAAAVtcUTN72973NHZaVScSwrcSx5xhge3TzhyQWkBsiEVuKhIPpZ2 3NIvnAVdEZq0QQF42hIVNvtOPSjj X-Google-Smtp-Source: APXvYqzpFW1CzgLw98PD/72sPPg8NB3PSq4oXycYNe2SpZF8qnbVCrWkpd4LxCG9CRlcBOHcdbg/Iw== X-Received: by 2002:a62:bd13:: with SMTP id a19mr2335442pff.222.1553007184562; Tue, 19 Mar 2019 07:53:04 -0700 (PDT) Received: from sjolley (c-71-59-136-149.hsd1.or.comcast.net. [71.59.136.149]) by smtp.gmail.com with ESMTPSA id v2sm22759170pfg.118.2019.03.19.07.53.03 (version=TLS1_2 cipher=ECDHE-RSA-AES128-GCM-SHA256 bits=128/128); Tue, 19 Mar 2019 07:53:03 -0700 (PDT) From: To: , Date: Tue, 19 Mar 2019 07:53:03 -0700 Message-ID: <031101d4de63$7488adb0$5d9a0910$@gmail.com> MIME-Version: 1.0 X-Mailer: Microsoft Outlook 16.0 Thread-Index: AdTeYv5XEB9JyTctTVS3ygWybvhNZw== Subject: Yocto Project Status WW12'19 X-BeenThere: openembedded-core@lists.openembedded.org X-Mailman-Version: 2.1.12 Precedence: list List-Id: Patches and discussions about the oe-core layer List-Unsubscribe: , List-Archive: List-Post: List-Help: List-Subscribe: , X-List-Received-Date: Tue, 19 Mar 2019 14:53:04 -0000 Content-Type: multipart/alternative; boundary="----=_NextPart_000_0312_01D4DE28.C82BF890" Content-Language: en-us ------=_NextPart_000_0312_01D4DE28.C82BF890 Content-Type: text/plain; charset="us-ascii" Content-Transfer-Encoding: 7bit Current Dev Position: YP 2.7 M3 (New feature Freeze has begun.) Next Deadline: YP 2.7 M3 Cutoff was Feb. 25, 2019 SWAT Team Rotation: * SWAT lead is currently: Armin * SWAT team rotation: Armin -> Paul on Mar. 23, 2019 * SWAT team rotation: Paul -> Ross on Mar. 30, 2019 * https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * M3 has not built yet however most major pieces are in place, including now, agreement on the new QA process. The delay is partly due to RP travel with others able to cover being unavailable for other reasons, combined with infrastructure issues. * The remaining questions for M3 are: * Public documentation of the new QA process * Upgrade for uninative for glibc 2.29 * Mesa upgrade? (unlikely given failures in testing) * The Yocto Project has updated to its new governance model which includes establishing a Technical Steering Committee (TSC) for Yocto Project. This is designed to complement and work alongside the OpenEmbedded TSC. Three members of the YP TSC are selected by the Yocto Project governing board and those people are Ross Burton, Khem Raj and Richard Purdie. The remaining two seats will be elected by OpenEmbedded. It is intended the TSC will take over the release process, SWAT team, bug triage and feature planning/development for 2.8. * YP 2.5.3 continues to be blocked on autobuilder-helper changes for the stable branches and the resulttool changes in master to move to the new QA process. * There is discussion on the openembedded-architecture list about changes to the stable branch patch criteria to bring us more into line with current industry best practices and thinking. Planned Releases for YP 2.7: * YP 2.7 M3 Cutoff was Feb. 25, 2019 * YP 2.7 M3 Release Target was Mar. 8, 2019 * YP 2.7 M4 Cutoff is Apr. 1, 2019 * YP 2.7 M4 Release Target is Apr. 26, 2019 Planned upcoming dot releases: * YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done. * YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done. * YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done. Tracking Metrics: * WDD 2432 (last week 2439) ( https://wiki.yoctoproject.org/charts/combo.html) * Poky Patch Metrics * Total patches found: 1526 (last week 1523) * Patches in the Pending State: 656 (43%) [last week 657 (43%)] Key Status Links for YP: https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status [If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!] Thanks, Stephen K. Jolley Yocto Project Project Manager * Cell: (208) 244-4460 * Email: sjolley.yp.pm@gmail.com ------=_NextPart_000_0312_01D4DE28.C82BF890 Content-Type: text/html; boundary="----=_NextPart_000_01B7_01D4D8B2.ACE42C40"; charset="us-ascii" Content-Transfer-Encoding: quoted-printable

Current Dev = Position: YP 2.7 M3 (New feature Freeze has = begun.)

Next Deadline: YP = 2.7 M3 Cutoff was Feb. 25, 2019

 

SWAT Team = Rotation:

 

Key = Status/Updates:

  • M3 has not built yet however = most major pieces are in place, including now, agreement on the new QA = process. The delay is partly due to RP travel with others able to cover = being unavailable for other reasons, combined with infrastructure = issues.
  • The remaining questions for M3 = are:
    • Public documentation of the new = QA process
    • Upgrade for uninative for glibc = 2.29
    • Mesa upgrade? (unlikely given = failures in testing)
  • The Yocto Project has updated = to its new governance model which includes establishing a Technical = Steering Committee (TSC) for Yocto Project. This is designed to = complement  and work alongside the OpenEmbedded TSC. Three members = of the YP TSC are selected by the Yocto Project governing board and = those people are Ross Burton, Khem Raj and Richard Purdie. The remaining = two seats will be elected by OpenEmbedded. It is intended the TSC will = take over the release process, SWAT team, bug triage and feature = planning/development for 2.8.
  • YP 2.5.3 continues to be = blocked on autobuilder-helper changes for the stable branches and the = resulttool changes in master to move to the new QA = process.
  • There is discussion on the = openembedded-architecture list about changes to the stable branch patch = criteria to bring us more into line with current industry best practices = and thinking.

 

Planned Releases = for YP 2.7:

  • YP 2.7 M3 Cutoff was Feb. 25, = 2019
  • YP 2.7 M3 Release Target was = Mar. 8, 2019
  • YP 2.7 M4 Cutoff is Apr. 1, = 2019
  • YP 2.7 M4 Release Target is = Apr. 26, 2019

 

Planned upcoming = dot releases:

  • YP 2.5.3 (Sumo) will be = targeted after YP 2.7 M2 is done.
  • YP 2.5.4 (Sumo) will be = targeted after YP 2.7 M4 is done.
  • YP 2.6.2 (Thud) will be = targeted after YP 2.5.4 is done.

 

Tracking = Metrics:

 

Key Status Links = for YP:

https://wiki.yoctoproject.or= g/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.or= g/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.or= g/wiki/Yocto_2.7_Features

 

The Status reports = are now stored on the wiki at: https://wiki.yocto= project.org/wiki/Weekly_Status

 

[If anyone has = suggestions for other information you’d like to see on this weekly = status update, let us know!]

 

Thanks,

 

Stephen K. Jolley<= o:p>

Yocto = Project Project Manager