Current Dev Position: YP 2.8 M2
Next Deadline: YP 2.8 Milestone 2 Cutoff July 14th, 2019
SWAT Team Rotation:
Next Team Meetings:
Key Status/Updates:
- 2.8 M1 has been released.
- Mailing lists issues are continuing to be worked on as a top priority.
- We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
- Several key reproducibility fixes have merged, thanks Joshua!
- The autobuilder has suffered stability issues with its NFS setup, seemingly related to the increased load from the new servers. We’re monitoring changes, hoping they fix the issue.
- We had significant problems with the versioning of libcrypt in recent distros which resulted in the need for a new uninative release. This fixes autobuilder builds.
Planned Releases for YP 2.8:
- M2 Cutoff 14th July
- M2 Release 26th July
- M3 Cutoff (Feature Freeze) 25th Aug
- M3 Release 6th Sept
- M4 Cutoff 30th Sept
- 2.8 (M4) Final Release 25th Oct
Planned upcoming dot releases:
- YP 2.7.1 (Warrior) is planned for build imminently now that 2.8 M1 is done but is pending the new uninative changes.
- YP 2.6.3 (Thud) is intended for build after 2.7.1 is complete and before 2.8 M2
Tracking Metrics:
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Project Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com