Current Dev Position: YP 2.8 M2
Next Deadline: YP 2.8 Milestone 2 Cutoff July 14th, 2019
SWAT Team Rotation:
Next Team Meetings:
Key Status/Updates:
- 2.7.1 is cleared for release and will be announced shortly
- 2.6.3 has two remaining issues before it can be built
- We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
- General patch backlog and merging is running back to normal
- Our numbers of patches in the metadata has been slowly decreasing and I wanted to mention how much we appreciate anyone doing cleanup of old/stale data. Over time it is making a significant difference!
- There are ongoing discussions on a few key topics which are summarised here for convenience. Please contribute if you have an interest in these areas:
- Running the testsuites for glibc/binutils/gcc
- Moving lsb to its own layer
- Removing poky-lsb in favour of some configuration fragments
- Reproducibility
- Minimising python2 dependencies
- Configuration of init systems
- Bitbake changes which change the way runqueue works quite radically have merged. If people see errors with setscene or normal task execution people do report them.
- Runqueue change to optimise sstate usage/sharing in multiconfig builds merged. Please report if its not working where you’d expect it to.
Planned Releases for YP 2.8:
- M2 Cutoff 14th July
- M2 Release 26th July
- M3 Cutoff (Feature Freeze) 25th Aug
- M3 Release 6th Sept
- M4 Cutoff 30th Sept
- 2.8 (M4) Final Release 25th Oct
Planned upcoming dot releases:
- YP 2.7.1 (Warrior) is ready for release.
- YP 2.6.3 (Thud) is intended for build after 2.7.1 is complete and before 2.8 M2
Tracking Metrics:
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Project Manager
( Cell: (208) 244-4460
* Email: sjolley.yp.pm@gmail.com