Current Dev Position: YP 2.8 M4 Feature Freeze

Next Deadline: YP 3.0 Final Release 25th Oct

 

SWAT Team Rotation:

 

Next Team Meetings:

 

Key Status/Updates:

 

Planned Releases for YP 3.0 {2.8}:

 

Planned upcoming dot releases:

 

Tracking Metrics:

 

Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

 

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:

https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

(    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm@gmail.com