Current Dev Position: YP 3.3 M3 development
Next Deadline: 1st March 2021 YP 3.3 M3 build and YP 3.3 Feature Freeze
Next Team Meetings:
Key Status/Updates:
- YP 3.2.2 has passed QA cleanly and awaiting final release approval.
- YP 3.1.6 has been built and is in QA.
- We have one week left before M3 is due to be built. This marks our feature freeze point for YP 3.3.
- We are trying to add rpm to reproducibility testing however there are several issues we need to resolve before that can merge.
- Looking through some of the patches in the “Pending” state, we have some really old stale ones which really need decisions to be made about their future. It would help a lot if recipe maintainers could recipe recipe patchsets and upstream them or remove them if they are no longer relevant.
- The glibc 2.33 issues encountered should now hopefully be resolved with the latest pseudo changes.
- Most of the successful AUH (Automatic Upgrade Helper) patches are now merged or queued however many of the failed upgrades have yet to be handled
- Intermittent autobuilder issues continue to occur and are now at a record high level. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
Ways to contribute:
YP 3.3 Milestone Dates:
- YP 3.3 M3 build date 2021/03/01
- YP 3.3 M3 Release date 2021/03/12
- YP 3.3 M4 build date 2021/04/05
- YP 3.3 M4 Release date 2021/04/30
Planned upcoming dot releases:
- YP 3.2.2 being reviewed for release.
- YP 3.1.6 is in QA.
- YP 3.2.3 build date 2021/03/15
- YP 3.2.3 release date 2021/03/26
- YP 3.1.7 build date 2021/03/29
- YP 3.1.7 release date 2021/04/09
Tracking Metrics:
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC
The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager