On 1/14/20 7:52 AM, Stephen Jolley wrote:

Current Dev Position: YP 3.1 M2

Next Deadline: YP 3.1 M2 build date 1/20/2020

 

Next Team Meetings:

 

Tip of the Week:

 

Key Status/Updates:

 

YP 3.1 Milestone Dates:

 

Planned upcoming dot releases:

New set of warrior patches sent out for review.


Back porting the remaining hash equivalence patches.

Do have some build failures that also affecting Master.

Will send out a call for patches sometime the end of next week.

Do we hold up the dot release if we add a new host?

- armin

 

Tracking Metrics:

 

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:

https://wiki.yoctoproject.org/wiki/TSC

 

The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status

 

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

(    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm@gmail.com