Yocto Technical Team Minutes for Mar. 5, 2019.

 

Attendees: Armin, Joshua, Randy, Richard, Joshua, Tim, Stephen, Tracey,
Michael, Alex,

 

YP Status: YP 2.7 M2 rc2 is being released today Mar. 5, 2019.

YP 2.7 M3 has a 4 items still to be resolved before the build.

YP 2.5.3 needs one major item to be resolved before it is built.

Richard discussed the status of M3 and the remaining work to be done, see
the status report.

Richard discussed the status of QA automation, need to backport the changes
to 2.5 and 2.6

Richard discussed the current SWAT status, need more attention and members.

Stephen discussed that next month's Technical meeting we will begin the
planning for YP 2.8.  The link for YP 2.7 Plan is at:
<https://docs.google.com/document/d/15jB6nUJU2wrtnu6w07L9RZpNlj6AoxSTPEX5aEL
ts1g/edit>
https://docs.google.com/document/d/15jB6nUJU2wrtnu6w07L9RZpNlj6AoxSTPEX5aELt
s1g/edit

Richard discussed the updates from YP Advisory Board, both Comcast upgrading
to Platinum and the new agreed to Governance plan for YP.  This allows the
creation of the YP TSC. (Technical Steering Committee.)

Richard discussed that we can't run vgl without GPU HW in the cluster. Need
to decide if we need GPU cards in any/all servers.

Richard discussed the status of bug 8729.

Armin discussed the changes planned for QA transition.  Need to update
documentation to reflect the changes. 

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

*    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm@gmail.com
<mailto:sjolley.yp.pm@gmail.com> 

 


[-- Attachment #2: Type: text/html, Size: 9656 bytes --]

^ permalink raw reply	[flat|nested] 8+ messages in thread
* YPTM minutes
@ 2019-04-02 15:50 sjolley.yp.pm
  0 siblings, 0 replies; 8+ messages in thread
From: sjolley.yp.pm @ 2019-04-02 15:50 UTC (permalink / raw)
  To: yocto

[-- Attachment #1: Type: text/plain, Size: 1287 bytes --]

Attendees: Stephen, Joshua, Alex, Jon, Randy, Richard, Michael, David,
Bruce, Shawn, Jaewon, Manjukum, Tracey, Chris, Tim, Chandana, Aitronics,
Paul, Tomas, Ross, 

 

YP 2.7 M3 rc1 is out of QA.  The YP 2.7 M3 rc1 report is summarized at
<https://lists.yoctoproject.org/pipermail/yocto/2019-April/044667.html>
https://lists.yoctoproject.org/pipermail/yocto/2019-April/044667.html and
the results are at
<https://autobuilder.yocto.io/pub/releases/yocto-2.7_M3.rc1/testresults/>
https://autobuilder.yocto.io/pub/releases/yocto-2.7_M3.rc1/testresults/.

YP 2.5.3 and YP 2.6.2 stable releases were built and submitted to QA last
week.

We discuss the YP 2.8 Ideas document at:
<https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJ
GXbU/>
https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJG
XbU/ - If you wish to edit the file, send a request. 

 

AR: Tim - Add to planning document details about installable images via WIC.


AR: Stephen - Cancel 4/16 engineering meeting and add 4/16 Planning meeting.

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

*    Cell:                (208) 244-4460

* Email:              sjolley.yp.pm@gmail.com
<mailto:sjolley.yp.pm@gmail.com> 

 


[-- Attachment #2: Type: text/html, Size: 8771 bytes --]

^ permalink raw reply	[flat|nested] 8+ messages in thread
* YPTM minutes
@ 2019-02-05 16:36 sjolley.yp.pm
  2019-02-05 18:11 ` Scott Rifenbark
  0 siblings, 1 reply; 8+ messages in thread
From: sjolley.yp.pm @ 2019-02-05 16:36 UTC (permalink / raw)
  To: yocto

[-- Attachment #1: Type: text/plain, Size: 1459 bytes --]

Yocto Technical Team Minutes for Feb. 5, 2019.

 

Attendees: Armin, David, Joshua, Randy, Tim, Richard G., Stephen, Jan-Simon,
Manjukum, Tracey, Trevor, Nick, Richard P, Mark, Kate, Michael, 

 

YP 2.6.1 was released on Feb. 4, 2019.

YP 2.7 M2 was built and is in QA and is 79% done.  See:
<https://wiki.yoctoproject.org/wiki/2.7_QA_Status>
https://wiki.yoctoproject.org/wiki/2.7_QA_Status

 

Armin agreed to add Ubuntu 18.4 to YP 2.6 series and we will use in for YP
2.7 

We discussed that the YP 2.6 manual doesn't have an upgrading to YP 2.6.
Tracey will look into this.

 

We discussed the status of YP 2.7 upgrades and we are doing OK there.  We
are struggling on new features YP 2.7.  Richard is primarily working to
stabilize the autobuilder to produce an automated QA report to allow QA to
transition from Intel. 

 

Richard discussed maintainers of OE-Core.  AUH is sending requests but not
getting feedback. 

 

Richard discussed that we have issues with some products and need support
from the community to fix.

 

Tim discussed ptest issues Richard has identified.

 

Richard asked if there were ideas about how to better communicate with the
community. No specific suggestions.

 

Thanks,

 

Stephen K. Jolley

Yocto Project Project Manager

*    Cell:                (208) 244-4460

* Email:               <mailto:sjolley.yp.pm@gmail.com>
sjolley.yp.pm@gmail.com

 


[-- Attachment #2: Type: text/html, Size: 6763 bytes --]

^ permalink raw reply	[flat|nested] 8+ messages in thread

end of thread, other threads:[~2019-04-02 15:50 UTC | newest]

Thread overview: 8+ messages (download: mbox.gz follow: Atom feed
-- links below jump to the message on this page --
2019-03-05 16:39 YPTM minutes sjolley.yp.pm
  -- strict thread matches above, loose matches on Subject: below --
2019-04-02 15:50 sjolley.yp.pm
2019-02-05 16:36 sjolley.yp.pm
2019-02-05 18:11 ` Scott Rifenbark
2019-02-05 18:24   ` Joshua Watt
2019-02-05 19:00     ` Scott Rifenbark
2019-02-05 21:05     ` akuster808
2019-02-05 21:56       ` Scott Rifenbark

This is an external index of several public inboxes,
see mirroring instructions on how to clone and mirror
all data and code used by this external index.