* Yocto Project Status WW28
@ 2016-07-08 16:11 Saul Wold
0 siblings, 0 replies; 2+ messages in thread
From: Saul Wold @ 2016-07-08 16:11 UTC (permalink / raw)
To: Yocto Discussion, OpenEmbedded List
[-- Attachment #1: Type: text/plain, Size: 2003 bytes --]
Current Dev Position: YP 2.2 M2
Next Deadline: YP 2.2 M2 cut off would
be: 7/18/16
SWAT team rotation: Bill -> Paul
https://wiki.yoctoproject.org/wiki/Yoct
o_Build_Failure_Swat_Team
Key Status/Updates:
* M1 QA report is out however there are concerns about performanceregressions which have not been root caused. M1 will continue to bedelayed until we figure out those issues and the fact that medium+ bugsand high bugs are still assigned to M1.
* M2 patch merging is held up due to the shear volume of regressionswe’re seeing which are basically being left to Ross/RP to triage andfind the patches responsible.
* We did upgrade pseudo after various issues which brings in severalxattr fixes and resolves the init problems we were seeing in pseudotowards the end of the last release properly, rather than theworkarounds we put in place.
* We’ve merged the progress patches from Paul so we get better feedbackduring the build for how various tasks are progressing.
* We’re looking likely to remove directfb from OE-Core since the projectappears to have died.
* 2.1.1 is in QA having had a successful build. We are working with areduced capacity QA team due to various changes at Intel/WindRiver sowe will have more limited QA testing of this unfortunately.
Key YP 2.2 Dates:
* YP 2.2 M1 release would be: 6/24/16
* YP 2.2 M2 cut off would be: 7/18/16
* YP 2.2 M2 release would be: 7/29/16
* YP 2.2 M3 cut off would be: 8/29/16
* YP 2.2 M3 release would be: 9/9/16
* YP 2.2 M4 cut off would be: 10/3/16
* YP 2.2 M4 release would be: 10/28/16
Tracking Metrics:
WDD 2747 (last week 2718)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features
[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]
[-- Attachment #2: Type: text/html, Size: 12233 bytes --]
^ permalink raw reply [flat|nested] 2+ messages in thread
* Yocto Project Status WW28
@ 2015-07-10 15:15 Jolley, Stephen K
0 siblings, 0 replies; 2+ messages in thread
From: Jolley, Stephen K @ 2015-07-10 15:15 UTC (permalink / raw)
To: yocto@yoctoproject.org, openembedded-core@lists.openembedded.org
[-- Attachment #1: Type: text/plain, Size: 1730 bytes --]
Current Dev Position: 1.9 Milestone 2 (M2)
Next Deadline: M2 cut off of July 27th at noon GMT
SWAT team rotation: Paul -> Ross
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
* Too many issues in 1.9M1 RC1 to release, moving to RC2.
* 1.9 M1 RC2 due to enter QA (build currently in progress)
* Many fixes for various random autobuilder failures, still more needed but patch queues somewhat unblocked
* Data store changes on Bitbake list, will merge on Monday assuming no major feedback
* No feedback on getVar expansion parameter changes. Fixes posted for meta-oe, will likely just merge if no objections
Key YP 1.9 Dates:
1.9 Feature Freeze Date/M3 Cut off: Aug. 24, 2015 noon GMT
YP Final/M4 Cut off: Sept. 28, 2015 noon GMT
1.9 M1 Release Target: Before July 10, 2015 (Will miss deadline.)
1.9 M2 Release Target: Before Aug. 14, 2015
1.9 M3 Release Target: Before Sept. 11 2015
1.9 final Release Target: Before Oct. 30, 2015
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.9_Status
https://wiki.yoctoproject.org/wiki/Yocto_1.9_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_1.9_Features
Tracking Metrics:
WDD 1684 (last week 1640)
(https://wiki.yoctoproject.org/charts/combo.html)
[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]
Thanks,
Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
* Work Telephone: (503) 712-0534
* Cell: (208) 244-4460
* Email: stephen.k.jolley@intel.com
[-- Attachment #2: Type: text/html, Size: 18288 bytes --]
^ permalink raw reply [flat|nested] 2+ messages in thread
end of thread, other threads:[~2016-07-08 16:11 UTC | newest]
Thread overview: 2+ messages (download: mbox.gz follow: Atom feed
-- links below jump to the message on this page --
2016-07-08 16:11 Yocto Project Status WW28 Saul Wold
-- strict thread matches above, loose matches on Subject: below --
2015-07-10 15:15 Jolley, Stephen K
This is a public inbox, see mirroring instructions
for how to clone and mirror all data and code used for this inbox